CLIENT:
Strandline Resources
LOCATION:
Murchison, WA
Execution Period:
June 2021 to January 2022
Contract value:
~$12 million
Scope of work
The scope of work includes the installation of buildings, infrastructure, services and support facilities to provide a fully functioning and operable accommodation village with a capacity of 272 persons, plus a 100 room temporary construction camp.
The Accommodation Village consists of self-contained accommodation units, central meals and social amenities area, recreational and grassed areas, central administration complex and support infrastructure (power water and services etc), delivered in four phases: